Technical Work Group
Fish Passage Center Oversight Board meeting
10:00am Status Reports
  • Temperature-correlated wind data (Koehler)
  • Hydro capacity survey – comments and what to do next (Koehler)
  • VB interface (Byrne)
10:30am Benchmarking
  • Stochastic Forced Outage Distribution (Diffely/Byrne)
    >> Presentation
  • Simulated vs. Real Hourly Dispatch (Diffely/Koehler/Fazio)
    >> Presentation
11:00am Resource Adequacy Assessment for 2015 (Fazio/Diffely/Koehler)
12:00pm LUNCH - On your own
1:00pm Resource Adequacy Assessment for 2015 (continued)
  • Last year’s assessment
  • Changes in loads, resources and the model
1:30pm Update on Methodology Review (Fazio)
>> Presentation
2:00pm PNUCC Big Wind Studies (Adams)
>> Attachment
2:30pm Work Plan and Schedule (Fazio/Diffely)
>> Spreadsheet
3:00pm Schedule Next Meeting / Adjourn